FY 2010/11 – FY 2011/12
CAPITAL BUDGET
Introduction and Framework
03/30/2010 San Francisco, California
Overview
· What is the Capital Budget?
· Previously Adopted Capital Budget
· Recent Capital Program Accomplishments
· Preliminary FY 2011 and FY 2012 Capital Budget
· Next Steps
Capital Budget
· The Capital Budget is a two year document
· Last adopted in June 2008
· Prepared in accordance with Prop A (Sect. 8A.106)
· Demonstrates Agency’s ability to make substantial progress in meeting Prop A performance standards (Sect. 8A.103)
· Establishes capital expenditure limits
· Documents the capital projects that will be prioritized to receive capital funding
Previously Adopted Capital Budget
FY 2009 | FY 2010 | Total | |
Adopted Budget | $762M | $353M | $1,115M |
Expenditures* | $88M | $157M | $245M |
* FY 2010 projected based on actuals through Jan. 2010
· The adopted budget included total funding of $1.1 billion
· FY 2009 included $353M in carry forward funding
· Budget assumed over $200M in transfers from the Operating budget that did not materialize
· Despite shrinking funding, staff still able to obtain grants totaling $192M in FY 2009 and $226M in FY 2010 (year-to-date)
Financial Crisis Impacts
· State Infrastructure Bonds (Prop 1B) reduced and delayed
· Central Subway full funding grant agreement timeline pushed
· Local sales tax revenues down
· Repackaged large projects to fit within funding constraints
· Operating budget deficits
Major Project Expenditures and Status
Project | FY 09 Budget Revenues | FY 09 Budget Expenditures | FY 09 Actual Expenditures | Project Challenges and Status |
Central Subway | $192.2 M | $23.1 M | $13.0 M | FTA Full Funding Agreement and State I-Bond funding delayed. Operating budget crisis impacted staffing and design schedule. Several large contracts pending. |
Rail Replacement | $ 20.8 M | $43.2 M | $ 3.1 M | Building funds needed to award contracts. 2 large contracts recently awarded and 1 close to advertising. |
Third Street LRT/MME | $ 45.7 M | $56.1 M | $ 8.7 M | Construction contract completed and spent soon after end of FY 09. |
LRV Overhaul | $ 25.4 M | $18.7 M | $ 0.1 M | Due to funding shortfall, project needed to be resized, with contract awarded in FY 10. |
Islais Creek | $ 51.2 M | $11.7 M | $ 0.8 M | I-bond loss led to project rescoping. Contract advertised and bids received in FY 10. |
Signs of a Turnaround
· Refined project scope to match available funding
· Establish revised implementation schedule to account for funding delays
· Reorganized to ensure staffing for critical programs
· FY 2010 estimated expenditures of $157M
· Many projects under contract or soon to be, leading to higher expenditures projected for FY 2011 and FY 2012
Capital Program Accomplishments: State of Good Repair
· Capital Asset Inventory Initiated
· Transit Vehicle Rehabilitation
· Radio Replacement
· Transit Infrastructure Replacement
· Traffic Signal Upgrades
Capital Program Accomplishments: Enhancement/Expansion
· Central Subway: Initiated Final Design & Utility Relocation, Groundbreaking (Feb. 2010)
· Metro East Light Rail Facility: Opened (Sept. 2008)
· SFgo: Phase 1 completed
· SFpark: Pilots initiated
· Bicycle Plan: 9 bike lane projects, bike parking and sharrows citywide
· Citywide Traffic Calming and Pedestrian Projects
Preliminary Budget Highlights
· Propose expenditure limits of $375M in FY 2011 and $377M in FY 2012
· Based on recent annual averages, plus several large, maturing projects:
– Central Subway
– Central Control & Communications (C3)
– Radio Communication System
– Islais Creek
– Automatic Fare Collection Program
– Fleet Procurement
· Funding has been awarded or is committed
Proposed Capital Budget: State of Good Repair
Project/Program | FY 2011 | FY 2012 | Total |
Fleet Procurements & Rehab | 92.0 M | 39.0 M | 131.0 M |
C3 (Central Control & Communications) | 22.0 M | 35.0 M | 57.0 M |
Islais Creek | 31.2 M | 20.8 M | 52.0 M |
Radio Communications System | 19.0 M | 26.0 M | 45.0 M |
Transit Infrastructure | 20.0 M | 20.0 M | 40.0 M |
Automatic Fare Collection Equipment | 16.0 M | 12.0 M | 28.0 M |
SFgo | 10.0 M | 10.0 M | 20.0 M |
Transit Facilities | 4.5 M | 4.5 M | 9.0 M |
Transit Equipment | 1.0 M | 1.0 M | 2.0 M |
Subtotal State of Good Repair | $215.7 M | $168.3 M | $384.0 M |
Proposed Capital Budget: Enhancement/Expansion
Project/Program | FY 2011 | FY 2012 | Total |
Fleet Procurements & Rehab | 92.0 M | 39.0 M | 131.0 M |
C3 (Central Control & Communications) | 22.0 M | 35.0 M | 57.0 M |
Islais Creek | 31.2 M | 20.8 M | 52.0 M |
Radio Communications System | 19.0 M | 26.0 M | 45.0 M |
Transit Infrastructure | 20.0 M | 20.0 M | 40.0 M |
Automatic Fare Collection Equipment | 16.0 M | 12.0 M | 28.0 M |
SFgo | 10.0 M | 10.0 M | 20.0 M |
Transit Facilities | 4.5 M | 4.5 M | 9.0 M |
Transit Equipment | 1.0 M | 1.0 M | 2.0 M |
Subtotal State of Good Repair | $215.7 M | $168.3 M | $384.0 M |
Next Steps
· April 20: Submit Capital Budget for adoption
· Capital Investment Plan (CIP):
– Coordinated with Central Subway Financial Plan
– Utilize new data management systems
· Quantitative analysis to establish Agency priorities
· Better match funding opportunities to capital projects
– Late Spring: Review Prioritization Approach
– Fall: Present CIP Update